Newmont Goldcorp has announced its Ahafo Mill Expansion (AME) project in Ghana successfully processed its first ore and on track to achieve commercial p...

Newmont Goldcorp has announced its Ahafo Mill Expansion (AME) project in Ghana successfully processed its first ore and on track to achieve commercial production in the Q4 2019.

The mill expansion will increase average annual gold production at the Ahafo mine by between 75,000 and 100,000 ounces for the first five years, beginning in 2020, with mill capacity expanding by more than 50% through the addition of a crusher, grinding mill and leach tanks. The project is expected to deliver an IRR of more than 20% and, together with other projects at Ahafo, will extend profitable production through at least 2029.

“Combined with Subika Underground, which was successfully completed in November 2018, the mill expansion will increase Ahafo’s production to between 550,000 and 650,000 ounces per year through 2024, while lowering life-of-mine processing costs,” said Tom Palmer, President. “The project also accelerates the efficient processing of stockpiled ore and supports profitable development of Ahafo’s highly prospective underground resources, which continue to demonstrate considerable upside.”

SEE ALSO:

Barrick Gold and Newmont Goldcorp launch Nevada Gold Mines

Newmont Mining Corporation: The growth of mining in Ghana

Newmont Goldcorp announced as world's biggest gold miner

Read the latest issue of Mining Global here

In 2019, Ahafo is expected to achieve record production – with improved costs – driven by higher grades from the Subika open pit, a full year of mining from the Subika Underground and the completion of the Ahafo Mill Expansion. Capital costs for the AME are estimated at between $140mn and $180mn and have been funded through free cash flow and available cash balances. Commercial production began at Ahafo in 2006, and in 2018 the operation sold 436,000 ounces of gold at all-in sustaining costs of $864 per ounce.i

Over the last six years, Newmont has successfully built 11 new mines, expansions and projects on four continents – on or ahead of schedule and at or below budget. These projects include Akyem and the Phoenix Copper Leach in 2013, the Turf Vent Shaft in 2015, Merian and Long Canyon in 2016, the Tanami Expansion in 2017, and Twin Underground, Northwest Exodus and Subika Underground in 2018, and the Tanami power project in 2019. 

Upon completion of the Newmont Goldcorp transaction earlier this year, the Company now holds the largest reserves and resources in the gold sector, with 90% located in the Americas and Australia. These assets allow the company to sequence profitable projects in its unmatched pipeline to sustain six to seven million ounces of steady gold production over a decades-long time horizon.

Share

Featured Articles

Australia Looks to Loosen China's Grip on Critical Minerals

New Australian government rules around foreign investment in critical minerals targets China dominance in critical minerals market

EY: Silver Miners' Sustainability & Supply Challenge

EY's LatAm energy leader Alfredo Alvarez Laparte on how silver miners can remain competitiveness in face of falling silver production and ESG demands

Caterpillar: Profile of a Mining Equipment Colossus

As Caterpillar shares fall due to falling machinery sales, we profile the mining & construction equipment multinational and its iconic yellow machines

BHP $38bn Anglo-American bid is 'all About Copper'

Supply Chain & Operations

GEM: Non-China Coal Power Sees First Growth Since 2019

Supply Chain & Operations

Biden Ruling 'Threat to US Critical Minerals Mining'

Supply Chain & Operations