Newmont Goldcorp’s Ahafo Mill hits commercial production in Ghana

By Daniel Brightmore
Newmont Goldcorp todayannounced that the Ahafo Mill Expansion in Ghana achieved commercial production, on schedule and within budget for approximately...

Newmont Goldcorp today announced that the Ahafo Mill Expansion in Ghana achieved commercial production, on schedule and within budget for approximately $175mn. 

Combined with the Subika Underground, which was successfully completed in November 2018, the mill expansion is expected to increase Ahafo’s average annual gold production to between 550,000 and 650,000 ounces per year through 2024, while lowering life-of-mine processing costs.

“The Ahafo Mill Expansion represents our third profitable project delivered on schedule and within budget in 2019, along with the Tanami Power project in Australia and the Borden mine in Canada,” said Tom Palmer, President and Chief Executive Officer. 

The mill expansion is expected to generate an internal rate of return of more than 20 percent at a $1,200 gold price, while also extending profitable production at Ahafo through at least 2029. I continue to be encouraged by Ahafo’s and Ghana’s mineral prospectivity and the potential for ongoing, profitable growth.”

SEE ALSO:

Newmont Goldcorp’s Ahafo mill expansion in Ghana yields first ore

Newmont Goldcorp top gold miner on Dow Jones sustainability index

Newmont Goldcorp opens Borden ‘mine of the future in Ontario

Read the latest issue of Mining Global here

Features and benefits of the mill expansion include:

  • Increasing mill capacity at Ahafo by more than 50% to nearly 10 million tonnes per year with the addition of a crusher, grinding mill and leach tanks to the circuit.
  • Adding annual gold production of 75,000 to 100,000 ounces per year for the first five full years beginning in 2020.
  • Accelerating efficient processing of ore from stockpiles and the Subika Underground mine, as well as harder, lower-grade ore from Ahafo’s existing pits.
  • Supporting profitable development of Ahafo’s highly prospective underground resources, which continue to demonstrate considerable upside.

Ahafo is expected to deliver record production this year - with improved costs - driven by higher grades from the Subika open pit, a full year of mining from the Subika Underground and the completion of the Ahafo Mill Expansion. Commercial production began at Ahafo in 2006, and in 2018 the operation sold 436,000 ounces of gold at all-in sustaining costs of $864 per ounce. 

Newmont Goldcorp has the strongest and most sustainable portfolio of operations, projects and exploration prospects in the gold sector. These assets allow the company to sequence profitable projects in its unmatched pipeline to sustain six to seven million ounces of steady gold production over a decades-long time horizon.

Share

Featured Articles

Laws Thwart US Bid to Match China on Lithium Mining

US bid to increase domestic production of lithium in order to reduce reliance on Chinese supplies of critical mineral frustrated by 'confusing' state laws

Bain: 'Inflation Dampening Mining Leaders' Net Zero Hopes'

Bain & Company’s annual Energy & Natural Resource Executive Survey shows 62% of energy execs say high costs mean net zero goals won't be met by 2060

Focus on: Lithium – ‘White Gold’ Driving the EV Revolution

Because of the move to electric vehicles, the metal lithium is rapidly becoming a vitally important part of world’s bid to move away from fossil fuels

Aluminium Industry Calls for new North America Body

Supply Chain & Operations

Data-Driven ABB Smart Hoisting Solution 'is Safety Boon'

Digital Mining

Deep Sea EV Metals Mining Firm in Greenpeace Clash

Sustainability